Pandemic puts brakes on dozens of road projects

toll-roads-Florida-Large
'Our goal was to retain all active projects to their completion.'

State transportation officials cut or delayed 77 road projects from a five-year plan as revenues dropped with more Floridians working remotely and people delaying travel plans because of the coronavirus pandemic.

This year, the Department of Transportation had to make up $763 million from lost gas taxes, rental car fees, toll collections, and other state and federal sources.

Stacy Miller, assistant secretary for finance and administration at the department, said Tuesday the affected road projects involve joint ventures with airports, seaports and local governments.

“Our goal was to retain all active projects to their completion, whether those were engineering or construction projects,” Miller told members of the Senate Transportation, Tourism, and Economic Development Appropriations Subcommittee. “We have not impacted any active projects at this time. And we don’t anticipate any changes.”

Sen. Ed Hooper, a Republican from Clearwater, and Sen. Janet Cruz, a Tampa Democrat, expressed concern that one of the 23 projects delayed will be the $1.4 billion Westshore interchange in Tampa.

Hooper said he anticipates hearing a lot of “anger” in pushing back the interchange work from the 2023-2024 fiscal year to the 2025-2026 fiscal year, while a rebuild goes forward of the Howard Frankland Bridge linking St. Petersburg with Tampa.

“In that five-year span, I cannot imagine what traffic congestion and mobility is going to be like with a rebuilt bridge, with probably eight or 10 lanes of incoming traffic, and southbound traffic, coming into an already congested Westshore interchange, where Tampa International Airport turns off a lot of the shopping and business,” Hooper said.

Miller said employees of the department and its District 7 office, which oversees the Tampa area, try to determine if there are ways to address the potential traffic issues during the gap years.

“We are working to try to creatively figure out a way to potentially advance that project in the future,” Miller said.

Last spring, Gov. Ron DeSantis pushed transportation officials to take advantage of reduced traffic during the pandemic to speed up road and bridge projects. The Howard Frankland Bridge was among the projects DeSantis directed the Department of Transportation to accelerate.

The agency estimated more than 650 calendar days of construction were saved by advancing the projects, which included widening Southern Boulevard in western Palm Beach County, working on flyovers that are part of the I-4 “Ultimate” project in Orlando, and construction of a “diverging diamond” interchange on Interstate 95 in Nassau County.

During Tuesday’s meeting, senators and Miller didn’t address three controversial toll-road projects in the five-year plan projected to require up to $101.7 million a year over the next decade.

The roads would extend the Suncoast Parkway from Citrus County to Jefferson County near the Georgia border, extend Florida’s Turnpike from Wildwood to connect with the Suncoast Parkway and create a new road linking Polk and Collier counties. They are each undergoing needs determinations. Economic and environmental feasibility studies will be conducted if a need is found for any part of the roads.

Sen. Tina Polsky, a Boca Raton Democrat, and Rep. Ben Diamond, a Democrat from St. Petersburg, filed legislation (SB 1030 and HB 763) last week to remove the projects, which were a priority of former Senate President Bill Galvano, from state law.

The department has long used what is known as the five-year work program to map out projects.

In addition to the current-year impacts, the state agency faces a $2.91 billion reduction in revenue over the next five years, according to August projections presented Tuesday to the Senate panel.

Starting at $303.6 million in the current fiscal year, toll collections are expected to account for $1.558 billion of the hit to revenue through the 2025-2026 fiscal year. In the same time, the department is expected to be short another $1.097 billion in revenue generated by gas taxes, rental car surcharges, and motor-vehicle license fees, according to the projections.

Meanwhile, the state’s allotment for the current fiscal year through the federal Fixing America’s Surface Transportation, or FAST Act, was $1.8 billion, $258 million less than in prior years.

Partially offsetting the losses, the state department received $470 million in federal pandemic relief funding available until Sept. 30, 2024. Florida also received a separate $39 million non-recurring federal allocation.

As part of his proposed record $96.6 billion budget for the upcoming 2021-2022 fiscal year, DeSantis included $9.47 billion for the five-year work program. The budget DeSantis signed in June for the current fiscal year included $9.2 billion for the work program. Lawmakers will consider DeSantis’ proposed budget to draw up a spending plan during the legislative session that starts March 2.

___

Republished with permission of The News Service of Florida.

Jim Turner

Jim Turner is a Capitol reporter for the News Service of Florida, providing coverage on issues ranging from transportation and the environment to Legislative and Cabinet politics, which are some of the areas he worked in 20 years with TCPalm in Palm Beach County and the Treasure Coast. Jim grew up in Millburn, New Jersey, where he started his journalism career providing weekly reports on the high school soccer team --- of which he was a member--- to the local Millburn Item. Jim received degrees in journalism and history from High Point University in North Carolina.


One comment

  • Sonja Fitch

    February 10, 2021 at 4:58 am

    So how in hell if the $4billion increase in Duffus Desantis budget going to be covered?

Comments are closed.


#FlaPol

Florida Politics is a statewide, new media platform covering campaigns, elections, government, policy, and lobbying in Florida. This platform and all of its content are owned by Extensive Enterprises Media.

Publisher: Peter Schorsch @PeterSchorschFL

Contributors & reporters: Phil Ammann, Drew Dixon, Roseanne Dunkelberger, A.G. Gancarski, Anne Geggis, Ryan Nicol, Jacob Ogles, Cole Pepper, Gray Rohrer, Jesse Scheckner, Christine Sexton, Drew Wilson, and Mike Wright.

Email: [email protected]
Twitter: @PeterSchorschFL
Phone: (727) 642-3162
Address: 204 37th Avenue North #182
St. Petersburg, Florida 33704




Sign up for Sunburn


Categories